Skip to main content
Capital Planning
Brandon Smith3 min read
Two professionals reviewing post-project analytics and performance dashboards overlooking a food manufacturing floor

A food facility completes a $900K equipment upgrade project. The project finished 4 weeks late and 12% over budget. The commissioning phase revealed performance gaps requiring additional troubleshooting.

The project team celebrates completion and moves on.

Two years later, the facility begins a second capital project with a similar scope. The project team encounters similar delays, similar cost overruns, similar commissioning issues—because no lessons were captured or applied from the first project.

This cycle repeats: Each project learns hard lessons, then organizational memory evaporates when team members rotate.

The Post-Project Review Process

Effective PPR (Post-Project Review) happens within 4-6 weeks of project completion, before memories fade and team disperses.

Participants:

  • Project Manager
  • Plant Manager
  • Key vendors/contractors
  • Operations team representatives
  • Finance (budget review)
  • External consultant (neutral facilitator, optional)

Agenda Items:

Schedule Performance

  • Original planned duration vs. actual
  • What caused delays? (3-4 biggest delays)
  • What accelerated completion? (2-3 areas that worked well)
  • Should similar projects plan differently?

Budget Performance

  • Original budget vs. actual cost
  • Change orders: justified or preventable?
  • Contingency usage: was allocation adequate?
  • Cost overruns: root causes and prevention for future projects

Quality and Performance

  • Did equipment meet specifications at commissioning?
  • What underperformed? Why?
  • Were FAT/SAT adequate?
  • Commissioning duration: adequate or compressed?

Scope and Change Management

  • How many change orders? Were they necessary or preventable?
  • Scope creep: controlled or excessive?
  • Clear approval process effectiveness

Risk and Issues

  • Top 5 risks that occurred: Were they mitigated effectively?
  • Top 5 risks that didn't occur: Were contingencies necessary?
  • Major issues and resolution timeline

The Lessons Learned Documentation

Capture findings in structured format:

For Future Similar Projects:

  • "If doing another CIP upgrade, complete electrical assessment in FEL-1 (we discovered $80K upgrade needed mid-project)"
  • "Allocate 10 additional days for controls integration (previous projects underestimated by 8-10 days consistently)"
  • "Budget 8% contingency for equipment price escalation (supplier prices increased 6-7% during our project)"

Organizational Practices:

  • "Design-build delivery worked better than traditional delivery for this project type"
  • "Equipment lead time risk critical: implement 8-week early ordering mandate"
  • "Commissioning phase critical: allocate 4-6 weeks minimum for FAT, SAT, ramp-up"

Vendor/Contractor Performance:

  • Document performance for future vendor selection
  • Identify contractors who performed well; engage in future projects

Capturing Organization Knowledge

Store lessons learned in searchable database or wiki:

  • By project type (CIP upgrades, facility expansions)
  • By functional area (electrical work, utility infrastructure)
  • By risk category (schedule, budget, technical)

Future project managers can search: "CIP upgrades" and find 3-5 previous lessons to inform planning.

The ROI

Organizations capturing and applying lessons learned typically see:

  • 20-30% improvement in schedule predictability
  • 15-25% improvement in budget accuracy
  • 10-15% reduction in commissioning delays
  • Better vendor selection based on historical performance

For food manufacturing companies, systematic post-project reviews ensure organizational learning, continuous improvement in capital project execution, and competitive advantage through institutional knowledge.