Skip to main content
Capital Planning
Brandon Smith3 min read
Engineer reviewing scope documentation and project diagrams in a food processing facility

A food facility's $800K CIP system project starts with well-defined scope. Partway through, requests emerge: "While we're upgrading, can we also improve the chemical storage system?" "Can the new CIP handle this product variant?" "Our supplier suggested a better valve—can we upgrade?"

Each request seems reasonable. Each is a small addition: $15K here, $20K there, $10K elsewhere. Six months later, the project has $150K in change orders. The budget is exceeded 18%. The schedule has slipped 6 weeks.

This is scope creep—the incremental addition of work beyond original scope.

Why Change Orders Happen

  1. Incomplete Original Scope: Requirements weren't fully understood upfront
  2. Discovered Conditions: Site conditions different than expected (infrastructure gaps, equipment conflicts)
  3. Stakeholder Additions: Different departments want improvements added mid-project
  4. Vendor Suggestions: Equipment manufacturers recommend upgrades
  5. Regulatory Changes: New requirements emerge during execution

Each is legitimate, but accumulation kills budgets.

The Three-Level Approval Process

Level 1: Determination ($0-$10K)

Plant manager and project manager jointly determine necessity:

  • Is this within original scope? (If yes, no change order needed)
  • Is this essential to functionality? (If no, defer to future project)
  • Can it be accomplished within schedule? (If no, cost rises due to expediting)

Level 2: Authorization ($10K-$50K)

Requires Plant Director + CFO approval:

  • Document why change is necessary
  • Provide three-quote comparison if possible
  • Identify impact on schedule and budget
  • Specify who pays (project or business unit requesting addition)

Level 3: Strategic Review ($50K+)

Requires PE Operations Team or Board approval:

  • Changes of this magnitude require executive visibility
  • May indicate scope definition failures during FEL
  • May indicate market opportunity (strategic addition vs. scope creep)

The Paper Trail That Matters

Effective change order management requires documentation:

  • Original scope statement (crystal clear)
  • Change request (submitted on standard form)
  • Change order approval (authorized before work starts)
  • Revised budget and schedule (documented)
  • Completion documentation (proof of installation and testing)

Without this discipline, disputes emerge: "We never approved that." "That was supposed to be in the original scope."

The Prevention Strategy

Better than managing change orders: Preventing unnecessary ones.

  1. Thorough FEL Studies: Identify requirements and site conditions upfront
  2. Clear Scope Statements: Document explicitly what IS and ISN'T included
  3. Strong Project Governance: Clear approval authority and decision-making
  4. Regular Status Meetings: Surface stakeholder requests early, evaluate impact
  5. Stakeholder Alignment: Get sign-off from all departments BEFORE project starts

The Cost Impact

Every $10K change order in a $800K project:

  • Adds 0.4% to project cost
  • Adds 2-3 days to schedule (at minimum)
  • Creates one approval and documentation requirement

Ten $10K changes = $100K overrun + 20-30 day schedule slip.

For food manufacturing companies, strong change order discipline and clear scope definition during planning prevents budget and schedule overruns that compound during execution.