Skip to main content
Capital Planning
Brandon Smith3 min read
Technician interacting with digital commissioning displays on processing equipment in a food manufacturing facility

A dairy facility completes a $600K CIP system upgrade on schedule and budget. The equipment is installed. Controls are programmed. Electrical connections are tested.

The project team declares success and moves on.

Six weeks later, operators report: Cycle times are inconsistent. Chemical consumption is 15% higher than expected. Downtime occurs weekly when the control system doesn't achieve setpoint.

The root cause: Commissioning was inadequate. The equipment was installed and functional, but not optimized for actual production conditions.

The Three Commissioning Phases

Phase 1: Factory Acceptance Testing (FAT)

Happens: At equipment manufacturer's facility BEFORE delivery

What it tests: Equipment works as specified in controlled conditions

Example: Separator achieves 10,000 gallons/hour throughput at lab conditions (ideal temperature, composition, flow)

Cost: $15K-$30K

Timeline: 2-4 days

Duration: 1-2 weeks to schedule and execute

Problem: FAT doesn't replicate your facility's conditions. Lab conditions rarely match production reality.

Phase 2: Site Acceptance Testing (SAT)

Happens: At your facility with your equipment, your utilities, your water quality, YOUR conditions

What it tests: Equipment works as specified at YOUR facility

Example: Same separator achieves 9,200 gallons/hour at actual facility (real water hardness, temperature variability, actual operator proficiency)

Cost: $30K-$60K

Timeline: 2-4 weeks

Duration: 3-6 weeks to schedule, execute, troubleshoot, retest

Value: Identifies performance gaps BEFORE going live

Phase 3: Production Ramp-Up

Happens: Full production with new equipment

What it accomplishes: Operator training, process refinement, performance documentation

Cost: Embedded (production team time)

Duration: 2-6 weeks depending on complexity

Value: Validates that equipment meets production targets at sustained rates

Why Commissioning Gets Skipped

Budget pressure: "We're at budget limit. Commissioning seems optional." Schedule pressure: "We need production to start immediately." False confidence: "Equipment passed FAT. It should work fine."

The result: Equipment that technically works but underperforms operationally. Hidden costs emerge over months: higher energy use, more downtime, lower capacity realization.

The Cost of Inadequate Commissioning

Poor commissioning typically results in:

  • 10-20% lower throughput than expected
  • 15-25% higher operating costs (energy, chemical, labor)
  • 5-10% more downtime due to control instability
  • 3-6 months to optimize performance (if pursued at all)

Adequate commissioning cost: $50K-$100K Value recovered from optimization: $150K-$300K annually

ROI: 150-300% in first year, then ongoing savings.

The Commissioning Roadmap

Adequate commissioning requires:

  • Detailed performance requirements documented (before project starts)
  • FAT at manufacturer validating specs
  • SAT at your facility with your conditions (4-6 weeks)
  • Production ramp-up with dedicated support (4-6 weeks)
  • Performance documentation proving targets achieved
  • Operator training and optimization

For food manufacturing companies, budgeting and scheduling adequate commissioning—especially SAT—is foundational to achieving expected project ROI and operational performance.